Project

DESIGN, CONSTRUCTION, OPERATION AND MAINTENANCE OF THE GAS PIPELINE “SUR DE TEXAS-TUXPAN (MARINO)” LOCATED IN THE STATES OF TAMAULIPAS AND VERACRUZ.

Sector: Hydrocarbons


Last Revision

September 17, 2024
Short Name of the Project:
0770 Texas South-Tuxpan (Marine) Gas Piline
Type of Investment:
Brownfield
Subsector:
Midstream
Asset (s):
 Gas Pipeline 772 KM 
Contract Currency:
US Dollars
Estimated Investment MXN:

36,098,100,000

Estimated Investment USD:

2,111,000,000

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Operation,  Maintenance

DESCRIPTION

The project consists of the design, construction, operation and maintenance of a gas pipeline with a capacity of 2,600 million cubic feet per day (MCFD). The length of the gas pipeline is 772 km and 42 inches diameter.

The pipeline is interconnected with the Nueces-Brownsville gas pipeline and the Tuxpan-Tula gas pipeline. This system supplies natural gas to the new generation plants located in the states of Tamaulipas and Veracruz.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  Provision of services
Term
35 years
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
36,098,100,000
USD
2,111,000,000
Payment Source
Rate
The payments will be made by CFE on a monthly basis, under two concepts agreed in the contract:
- Fixed Capacity Fee: Reserved capacity available for CFE.
- Variable Use Fee: Variable costs to cover the operation and maintenance of the system (taxes, insurance, consumables, etc.)

STATUS

Stage
  Operation
Substage
  > 5 years of operation
RELEVANT DATES
Request for proposals/Announcement October 15, 2015
Proposals Reception May 19, 2016
Ruling June 13, 2016
Contract Signing June 20, 2016
Operation Starting Date September 17, 2019
Term of the Contract 2054
Contractor
Infraestructura Marina del Golfo  
Major Contractor’s Shareholders
TransCanada, Infraestructura Energética Nova

GEOLOCATION

State(s)
Tamaulipas, Veracruz   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Subdirección de Negocios No Regulados

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The project aims to expand energy infrastructure at a lower cost and with minimal environmental impact through the design, construction, operation, and maintenance of a gas pipeline with a capacity of 2,600 million cubic feet per day (MMCFD), measuring 772 km in length and 42 inches in diameter.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
Diario Oficial de la Federación
Description
A Constitutional Government of the United Mexican States Body, which has the function of publishing in the national territory: laws, regulations, agreements, circulars, orders and other acts issued by the powers of the Federation.
Responsive image
Source
CompraNet
Description
Electronic platform that provides government information of procurements, leases, services, public works, and other related services. Through this platform, the Federal Government ensures the transparency and agility of public procurement. Any interested person can follow the process from beginning to end.
ID
918243
Website
Responsive image
Source
Comisión Federal de Electricidad
Description
State owned productive company involved in power generation, transmission, distribution, commercialization and supply activities.
Responsive image
Source
Secretaría de Energía
Description
Federal Government entity responsible for controlling, managing and regulating Mexico’s energy resources, and establishing the national energy policy.
Responsive image
Source
Social Witness
Description
Figure who oversees that throughout a bidding procedure the current law is complied with, as a mechanism to strengthen transparency and minimize risks of opacity and corruption in government contracting.
Responsive image
Source
Concessionaire / Related Company

REMARKS

Contract SE-DM-STTX-005-2016.