Project

DESIGN, CONSTRUCTION, EQUIPMENT, INSTALLATION, OPERATION AND MAINTENANCE OF A PHOTOVOLTAIC POWER PLANT, IN THE STATE OF ZACATECAS.

Sector: Electricity


Last Revision

November 04, 2024
 
Short Name of the Project:
0713 CENACE. 3rd Long Term Power Auction (SLP 1/2017) Calera
Type of Investment:
Brownfield
Subsector:
Solar Power
Asset (s):
 Solar Farm 80 MW 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

1,456,140,000

Estimated Investment USD:

85,154,385

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Equipment,  Installation,  Operation,  Maintenance

DESCRIPTION

The project consists of the design, construction, equipment, installation, operation and maintenance of “Calera” photovoltaic power plant with a total production capacity of 80 MW in the state of Zacatecas. The plant has the following features:
Power Zone: National
Export Area: “Occidental”
Price Area: Aguascalientes
Interconnection Zone: CALERA INDUSTRIAL-(CAL-115)-115

The consortium integrated by Mitsui and Trina Solar, was assigned the following contract through CENACE's 2017 long-term power auction:

Contract number: SLP2017010123-001 related to:
- Energy for 189,928 MWHr/Year during 15 years and Renewable Energy Certificates (CEL) for 189,928 CEL/Year during 20 years, with an offered price of MXN$71,927,994

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Private
Type of Contract
  Assignment
Term
15 years
Selection Process
Public Auction
Financing Sources
Private
100 %
MXN
1,456,140,000
USD
85,154,385
Payment Source
Project revenues / Rate
The Clearing House is responsible for making the corresponding payments, derived from the following Electric Coverage Contracts with buyers and sellers:
- “Entidades Responsables de Carga” and the Clearing House
- Clearing House and the Generators

STATUS

Stage
  Operation
Substage
  < 5 years of operation
RELEVANT DATES
Request for proposals/Announcement May 08, 2017
Proposals Reception November 08, 2017
Ruling November 22, 2017
Contract Signing April 13, 2018
Execution/Construction Starting Date July 01, 2019
Operation Starting Date June 30, 2023
Term of the Contract 2036
Contractor
Mitre Calera Solar  
Major Contractor’s Shareholders
Mitsui, Trina Solar

GEOLOCATION

State(s)
Zacatecas   

SPONSOR

ADDITIONAL INFORMATION

Responsive image
Source
Centro Nacional de Control de Energía
Description
Public entity whose objective is to exercise operational control over the national electric system and the operations of the wholesale electricity market, and to guarantee impartial access to the national transmission network and to the general distribution network
Responsive image
Source
Comisión Reguladora de Energía
Description
The Energy Regulatory Commission is an independent regulatory entity that fosters the efficient growth of the sector, as well as of a reliable power supply. Its mission is to regulate the activities of the power industry in a transparent, impartial, and efficient manner, in order to generate the required certainty that encourages productive investment, promotes healthy competition, and generates an adequate coverage of services.
ID
E/1989/GEN/2017
Permit
ID
Proemio: E/1989/GEN/2017
Resolutions Additional Information
Responsive image
Source
Secretaría de Medio Ambiente y Recursos Naturales
Description
Federal government entity and sectorial authority responsible for establishing the necessary criteria and instruments to guarantee the protection, preservation, and use of natural resources, by developing an environmental policy that ensures sustainable growth.
ID
32ZA2017ED010
Permits

Follow the Project

Leave your e-mail to receive updates on this Project.

 I have read and I accept the Privacy Notice