Project

DESIGN, CONSTRUCTION, EQUIPMENT, OPERATION AND MAINTENANCE OF THE ATOTONILCO WASTE WATER TREATMENT PLANT IN HIDALGO.

Sector: Water and Environment


Last Revision

March 04, 2024
Short Name of the Project:
0598 WWTP Atotonilco
Type of Investment:
Brownfield
Subsector:
Water sanitation
Asset (s):
 Wastewater Treatment Plant 35,000 litres per second (l/s) 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

10,260,216,276

Estimated Investment USD:

600,012,647

Banobras, Fonadin involvement Banobras/Fonadin involvement

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Equipment,  Operation,  Maintenance

DESCRIPTION

The project consists of the construction of the Atotonilco Wastewater Treatment Plant (WWTP), in Hidalgo. It has a treatment capacity of 23,000 l/s and additional capacity of 12,000 l/s in the rainy season. The WWTP is designed to treat about 60% of the water wasted generated in Mexico's Valley.

(*) Project with Banobras and/or National Infrastructure Fund (Fonadin) involvement or support.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  Provision of services
Term
25 years
Selection Process
International Open Tender
Payment Source
Budgetary
The Federal Government, trough the multi-annual budget authorized to the National Water Comission (COANGUA), pays the private developer for the services delivery.

STATUS

Stage
  Operation
Substage
  > 5 years of operation
RELEVANT DATES
Request for proposals/Announcement May 12, 2009
Proposals Reception December 03, 2009
Ruling December 18, 2009
Contract Signing January 07, 2010
Execution/Construction Starting Date July 26, 2010
Operation Starting Date 2016
Term of the Contract July 27, 2035
Contractor
Aguas Tratadas del Valle de México  
Major Contractor’s Shareholders
IDEAL, Promotora de Desarrollo de América Latina, S.A. de C.V., Atlatec, Acciona Agua, S.A. de C.V., Desarrollo y Construcciones Urbanas

GEOLOCATION

State(s)
Hidalgo   

SPONSOR

Responsive image
Entity
Comisión Nacional del Agua
Department
Coordinación de Proyectos Especiales de Agua y Saneamiento
Contact
Coordinador General, Ildefonso Gonzalez Morales
E-mail
Ildefonso.gonzalez@conagua.gob.mx

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The Project allows the treatment of the wastewater of 12.6 million residents in the Metropolitan Area of ​​the Valley of Mexico. Among the several benefits is the reuse of treated water for agricultural irrigation and the reduction of greenhouse gases, since the plant has a cogeneration system for electrical energy that uses methane gas from sludge digestion residual.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
Secretaría de Medio Ambiente y Recursos Naturales
Description
Federal government entity and sectorial authority responsible for establishing the necessary criteria and instruments to guarantee the protection, preservation, and use of natural resources, by developing an environmental policy that ensures sustainable growth.
ID
13HI2013H0004
Procedures
Responsive image
Source
Comisión Nacional del Agua
Description
Deconcentrated entity in charge of preserving national waters and related public assets, guaranteeing water availability in co-responsibility with state and municipal governments.
Responsive image
Source
Concessionaire / Related Company
Responsive image
Source