Project

DESIGN, CONSTRUCTION, EQUIPMENT, INSTALLATION, OPERATION AND MAINTENANCE OF A WIND POWER PLANT IN THE STATE OF YUCATaN.

Sector: Electricity


Last Revision

August 05, 2024
 
Short Name of the Project:
0589 CENACE. 1st Long Term Power Auction (SLP-1/2015) Parque Eólico Tizimín
Type of Investment:
Brownfield
Subsector:
Wind Power
Asset (s):
 Wind Farms 84 MW 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

3,076,920,000

Estimated Investment USD:

179,936,842

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Equipment,  Installation,  Operation,  Maintenance

DESCRIPTION

The project consists of the design, construction, equipment, installation, operation and maintenance of “Tizimín” eolic power plant with a total production capacity of 84 MW in the state of Yucatan. The plant has the following features:
Power Zone: Nacional
Export Subarea: “Peninsular”
Price Area: Merida
Interconnection Zone: TIZIMIN TZM-115

Energía Limpia, was assigned the following contract through CENACE's 2015 long-term power auction:

Contract number: SLP-2015010455-02 related to:
- Energy for 291,900 MWHr/Year during 15 years and issue Renewable Energy Certificates (CEL) for 291,900 CEL/Year during 20 years, with an offered price of MXN$338,331,511

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Private
Type of Contract
  Assignment
Term
15 years
Selection Process
Public Auction
Financing Sources
Private
100 %
MXN
3,076,920,000
USD
179,936,842
Payment Source
Project revenues / Rate
Electric Coverage Contract between “Suministro Básico” (Public Service Regulatory Entity) and the Generator.

STATUS

Stage
  Operation
Substage
  > 5 years of operation
RELEVANT DATES
Request for proposals/Announcement November 30, 2015
Proposals Reception January 20, 2016
Ruling March 31, 2016
Contract Signing July 12, 2016
Execution/Construction Starting Date March 27, 2018
Operation Starting Date March 01, 2019
Term of the Contract 2034
Contractor
Consorcio Energía Limpia 2010  
Major Contractor’s Shareholders
Alarde Sociedad de Energía

GEOLOCATION

State(s)
Yucatan   

Entity in charge of controlling the possession of communal land, as well as providing documentary legal security derived from the application of the Agrarian Law, and is the operator of the Geospatial Information System (SIG).

SPONSOR

Responsive image
Entity
Private
Department
Consorcio Energía Limpia 2010

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The project aims to increase the use and consumption of renewable energy, and to contribute to the development of rural communities in the region.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
Secretaría de Medio Ambiente y Recursos Naturales
Description
Federal government entity and sectorial authority responsible for establishing the necessary criteria and instruments to guarantee the protection, preservation, and use of natural resources, by developing an environmental policy that ensures sustainable growth.
ID
31YU2016E0022
Permits
Responsive image
Source
Secretaría de Energía
Description
Federal Government entity responsible for controlling, managing and regulating Mexico’s energy resources, and establishing the national energy policy.
Responsive image
Source
Centro Nacional de Control de Energía
Description
Public entity whose objective is to exercise operational control over the national electric system and the operations of the wholesale electricity market, and to guarantee impartial access to the national transmission network and to the general distribution network
Responsive image
Source
Comisión Reguladora de Energía
Description
The Energy Regulatory Commission is an independent regulatory entity that fosters the efficient growth of the sector, as well as of a reliable power supply. Its mission is to regulate the activities of the power industry in a transparent, impartial, and efficient manner, in order to generate the required certainty that encourages productive investment, promotes healthy competition, and generates an adequate coverage of services.
ID
E/1787/GEN/2016
Permit
ID
Proemio: E/1787/GEN/2016
Resolutions Additional Information

REMARKS

The electricity generation project is carried out in two stages:
First stage: with start of operations on September 28, 2018
Second stage: with start of operations on March 1, 2019

Follow the Project

Leave your e-mail to receive updates on this Project.

 I have read and I accept the Privacy Notice