Project
DESIGN, CONSTRUCTION, EQUIPMENT AND INSTALLATION OF AN ELECTRICAL SUBSTATION, TRANSMISSION LINE, A CAPACITOR AND TERMINAL EQUIPMENT IN THE STATE OF NUEVO LEON.
Sector: Electricity
Last Revision
October 25, 2024
Short Name of the Project:
0422 CFE: Transmission Lines System 1821 Distribution Divisions (Phase 12)
Type of Investment:
Greenfield
Subsector:
Transmission / Distribution
Asset (s):
Power Station /Electrical Substation 40 MVA, Electric Power Transmission Line 7 km-c, Capacitor 2.40 MVAr
Contract Currency:
US DollarsEstimated Investment MXN:
N.A.
Estimated Investment USD:
N.A.
Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
Design, Construction, Equipment, Installation