Project

DESIGN, CONSTRUCTION, EQUIPMENT, INSTALLATION, OPERATION AND MAINTENANCE OF THE NORTHWEST COMBINED CYCLE POWER PLANT, IN THE STATE OF SINALOA.

Sector: Electricity


Last Revision

February 01, 2024
 
Short Name of the Project:
0221 CFE: Northwest Combined Cycle Power Plant
Type of Investment:
Brownfield
Subsector:
Thermic Power
Asset (s):
 Combined Cycle Power Plant 777 MW 
Contract Currency:
US Dollars
Estimated Investment MXN:

5,719,838,576

Estimated Investment USD:

334,493,484

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Equipment,  Installation,  Operation,  Maintenance

DESCRIPTION

Construction, installation, operation and maintenance of a combined cycle power plant with a net capacity of 777 MW, in the northwest of the state of Sinaloa.

The plant includes:
- 4 to 6 gas turbines.
- 1 steam turbine.
- 4 to 6 heat recovery units.
- 1 dry type cooling system with wind turbines.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  Provision of services
Term
25 years
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
5,719,838,576
USD
334,493,484
Payment Source
Project revenues / Rate
CFE purchases from the External Energy Producer (PEE) the generated energy.

STATUS

Stage
  Operation
Substage
  > 5 years of operation
RELEVANT DATES
Ministry of Finance Registration or equivalent August 01, 2011
Request for proposals/Announcement November 17, 2015
Proposals Reception March 01, 2016
Ruling April 04, 2016
Contract Signing April 22, 2016
Execution/Construction Starting Date June 22, 2016
Operation Starting Date October 15, 2019
Term of the Contract 2044
Contractor
Iberdrola Energía Noroeste  
Major Contractor’s Shareholders
Iberdrola

GEOLOCATION

State(s)
Sinaloa   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Gerencia de Licitación y Contratación de Proyectos de Inversión Financiada

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

This project responds to the need of increasing generation capacity in the northwest region of the country. Sustainability aspects are considered in the implementation of comprehensive environmental management plans and safety and health management at work.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
CompraNet
Description
Electronic platform that provides government information of procurements, leases, services, public works, and other related services. Through this platform, the Federal Government ensures the transparency and agility of public procurement. Any interested person can follow the process from beginning to end.
ID
944058
Website
Responsive image
Source
Comisión Reguladora de Energía
Description
The Energy Regulatory Commission is an independent regulatory entity that fosters the efficient growth of the sector, as well as of a reliable power supply. Its mission is to regulate the activities of the power industry in a transparent, impartial, and efficient manner, in order to generate the required certainty that encourages productive investment, promotes healthy competition, and generates an adequate coverage of services.
ID
E/1789/PIE/2016
Permit
ID
E/2050/GEN/2018
Permit Resolutions
Additional information

REMARKS

ID: CC NOROESTE 1118T0Q003 "Topolobampo II".