EXECUTION OF WORKS 245: ELECTRICAL SUBSTATION AND TRANSMISSION LINES, IN THE STATE OF SINALOA.

Sector: Electricity


Last Revision

April 01, 2025
 
Short Name of the Project:
0941 CFE: 246 SE 1320 Northwest Distribution (6th phase)
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
 Power Station /Electrical Substation 115 KV, Electric Power Transmission Line 115 KV, Electric Power Transmission Line 115 KV 
Contract Currency:
US Dollars
Estimated Investment MXN:

432,589,074

Estimated Investment USD:

23,383,193

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2025: $ 18.5
Contract Scope:
  Design,  Construction,  Equipment,  Installation

DESCRIPTION

The project consists of the execution of the following works:

- 1 substation with a voltage of 115 kV, with 1 feeder, ROSARIO (EXTENSION); and
- 2 transmission lines with a voltage of 115 kV and a total length of 68.5 km-Line and 78.1 km-Circuit, LT VILLA UNION - ROSARIO and LT ROSARIO - ESCUINAPA.

The works include the following concepts: supply of equipment and materials for permanent installation, development of engineering associated with electromechanical and civil design concepts, execution of electromechanical and civil works, pre-operational testing, as well as the preparation, analysis and evaluation of required studies (geotechnical studies, topographic surveys, census of underground installations, and resistivity) and the implementation of training and education programs

The contract will be for turnkey work at a fixed price with a maximum contract price of USD $25,383,435.99, the CFE will not grant an advance payment.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Financed Public Works
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
432,589,074
USD
23,383,193
Payment Source
Budgetary

STATUS

Stage
  Bidding
Substage
  Formalization
RELEVANT DATES
Request for proposals/Announcement December 12, 2024
Proposals Reception March 04, 2025
Ruling April 01, 2025
Contract Signing April 21, 2025
Execution/Construction Starting Date April 28, 2025
Term of the Contract June 21, 2026
Contractor
Consorcio Ingenieros de Guanajuato  

GEOLOCATION

State(s)
Sinaloa   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Subdirección de Contratación y Servicios
Contact
Mtra. Erika Alejandra Enciso Macías
E-mail
gcia.contratacionesdeobra@cfe.mx

ADDITIONAL INFORMATION

Responsive image
Source
Comisión Federal de Electricidad
Description
State owned productive company involved in power generation, transmission, distribution, commercialization and supply activities.
ID
CFE-0003-CACOA-0016-2024
Tender

REMARKS

Project ID: 0718TOQ0033.