Project

EXECUTION OF WORKS 280: SUBSTATIONS AND TRANSMISSION LINE, IN THE STATE OF SINALOA.

Sector: Electricity


Last Revision

April 09, 2024
 
Short Name of the Project:
0939 CFE: Transmission Line System 280 North Distribution 6th phase
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
 Power Station /Electrical Substation 2, Electric Power Transmission Line 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Equipment,  Installation

DESCRIPTION

The project consists of the execution of the following works:

- 2 substations with a voltage of 115 kV, with a total capacity of 20 MVA of transformation, 1.2 MVar of compensation and 2 feeders; and
- 1 transmission line with a voltage of 115 kV and a total length of 9.5 km-Circuit.

The works include within their scope the following concepts: supply of equipment and materials for permanent installation, development of the engineering associated with the electromechanical and civil design concepts, execution of the electromechanical and civil works, performance of pre-operational tests, as well as the preparation, analysis and evaluation of the required studies (geotechnical studies, topographic surveys, census of underground facilities, and apparent electrical resistivity of the terrain) and the delivery of training and coaching programs.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Financed Public Works
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
N.A.
USD
N.A.
Payment Source
Budgetary

STATUS

Stage
  Preinvestment
Substage
  Preparation
RELEVANT DATES

GEOLOCATION

State(s)
Sinaloa   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Subdirección de Contratación y Servicios
Contact
Mtra. Erika Alejandra Enciso Macías
E-mail
alejandra.encisom@cfe.mx

ADDITIONAL INFORMATION

Responsive image
Source
Comisión Federal de Electricidad
Description
State owned productive company involved in power generation, transmission, distribution, commercialization and supply activities.

REMARKS

The previous contest CFE-0003-CACOA-0026-2023 was declared void on Mar. 20, 2024 .