Project
EXECUTION OF WORK: SUBSTATIONS, IN THE STATES OF SAN LUIS POTOSI AND THE STATE OF MEXICO.
Sector: Electricity
Last Revision
November 19, 2024
Short Name of the Project:
0935 CFE: SLT 358 Increase in transmission capacity from northeast to center of the country, phase 1
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
Power Station /Electrical Substation 2
Contract Currency:
US DollarsEstimated Investment MXN:
1,777,967,164
Estimated Investment USD:
103,974,688
Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
Design, Construction, Equipment, Installation