Project
EXECUTION OF WORKS 352: SUBSTATIONS, DISTRIBUTION LINE AND TRANSMISSION LINES, IN THE STATE OF CAMPECHE.
Sector: Electricity
Last Revision
October 25, 2024
Short Name of the Project:
0928 CFE: Transmission Line System 352 Transformation and Transmission Querétaro, Isla del Carmen, Nuevo Casas Grandes and La Huasteca.
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
Power Station /Electrical Substation 4, Electric Power Transmission Line 3
Contract Currency:
Mexican Pesos MXNEstimated Investment MXN:
N.A.
Estimated Investment USD:
N.A.
Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
Design, Construction, Equipment, Installation