Project
EXECUTION OF WORKS: CONSTRUCTION OF 1 NEW TRANSMISSION LINE WITH 115 KV VOLTAGE REGIOMONTANO – LADRILLERA, 3 CAPACITOR BANKS AT 115 KV, IN THE STATE OF NUEVO LEÓN.
Sector: Electricity
Last Revision
October 25, 2024
Short Name of the Project:
0927 CFE: Expansion of the 115 kV Electrical Grid of the Tecnológico-Lajas corridor
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
Electric Power Transmission Line, Capacitor Bank 3
Contract Currency:
Mexican Pesos MXNEstimated Investment MXN:
400,715,124
Estimated Investment USD:
23,433,632
Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
Construction, Equipment, Installation