Project

MODERNIZATION OF THE JUAN CAPITÁN – EL CHIHUE HIGHWAY, CALLED “RUMBO NUEVO”, IN THE STATE OF TAMAULIPAS.

Sector: Transport


Last Revision

June 03, 2024
 
Short Name of the Project:
0923 Modernization of the "Rumbo Nuevo" highway, in Tamaulipas
Type of Investment:
Brownfield
Subsector:
Highways / bridges
Asset (s):
 Highway 37 KM-A2 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

1,447,028,170

Estimated Investment USD:

84,621,530

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Modernization,  Operation,  Maintenance,  Conservation

DESCRIPTION

The project consists of the design, construction and rehabilitation in order to provide the road service that allows the operation, maintenance and conservation of the state highway type A2 with a length of 37.0 km that begins at the junction of Federal Highway 85, and State Highway 9, and the Heavy Traffic Bypass of Cd. Victoria, and concludes by connecting with Federal Highway 101 before the Bridge over the Chihue River, in the Ejido San Antonio, for a period of 30 years, including auxiliary services and the set of all activities that the developer is obliged to and in exchange for obtaining the collection rights derived from the exploitation of the road.

Everything necessary for the “fine-tuning” of the communication route, construction of the toll plaza, gauging and information technology systems, the conservation required to maintain the requested level of service, the operation must be considered. of the services offered, and what is necessary for the correct operation of the highway.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  State PPP
Term
30 years
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
1,447,028,170
USD
84,621,530
Payment Source
Project revenues / Rate
The main project’s source of payment are the toll fees collected by the concessionaire.

STATUS

Stage
  Execution
RELEVANT DATES
Request for proposals/Announcement October 17, 2023
Proposals Reception December 01, 2023
Ruling December 11, 2023
Contract Signing January 08, 2024
Execution/Construction Starting Date February 19, 2024
Operation Starting Date January 08, 2025
Contractor
Promotora y Operadora de Infraestructura, y Grupo Concesionario de México  

GEOLOCATION

State(s)
Tamaulipas   

SPONSOR

Responsive image
Entity
State Government
Department
Gobierno del Estado de Tamaulipas
Secretaría de Obras Públicas
Contact
Ing. Pedro Cepeda Anaya
E-mail
pedro.cepeda@tamaulipas.gob.mx

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

Rehabilitation of the highway called “Rumbo Nuevo”, in the State of Tamaulipas, as well as its conservation, maintenance and operation for a period of 30 years, through a CAPP. The PNS has studies that guarantee the technical viability of the project, however, not enough elements were found to be able to carry out a more in-depth analysis of sustainability practices.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
State Government
ID
LPI-APP-001-2023
Convocatoria Tender call site
Responsive image
Source
Mexican Stock Exchange
ID
PINFRA
Listed Company

REMARKS

The project originates from the presentation of the unsolicited proposal of the company Grupo Concesionario de México, S.A. de C.V., by letter dated July 13, 2023.

Follow the Project

Leave your e-mail to receive updates on this Project.

 I have read and I accept the Privacy Notice