Project

DESIGN, CONSTRUCTION, OPERATION, MAINTENANCE, CONSERVATION AND EXPLOITATION OF THE ATLACOMULCO-POLOTITLÁN HIGHWAY, IN THE STATE OF MEXICO.

Sector: Transport


Last Revision

June 03, 2024
Short Name of the Project:
0913 Atlacomulco-Polotitlán Highway
Type of Investment:
Greenfield
Subsector:
Highways / bridges
Asset (s):
 Highway 82.80 KM-A4 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

19,000,000,000

Estimated Investment USD:

1,111,111,111

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Operation,  Maintenance,  Conservation,  Exploitation

DESCRIPTION

The project consists of the design, construction, operation, conservation, maintenance and exploitation of the "Atlacomulco-Polotitlán" highway type A-4, with a crown width of 22 meters, it will have 4 traffic lanes of 3.5 meters wide, two in each direction, 3.0 meters wide exterior boundaries, 1.0 meters internal boundaries and separating barrier of senses.

It includes the construction of 4 uneven junctions and incorporates 1 railroad crossing, 11 bridges and 3 viaducts, beginning the line on the Toluca – Polotitlán federal highway starting in the town of San Francisco and ending in Polotitlán with a junction on the Mexico - Querétaro Highway, with a total length of 82.80 kilometers, with an impact on the municipalities of Atlacomulco, Acambay, Aculco, Ixtlahuaca, in the State of Mexico.

FIRST AMENDMENT AGREEMENT (May 24, 2023). The contract term is extended to 53 years from the date of signing.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  State Concession
Term
53 years
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
19,000,000,000
USD
1,111,111,111
Payment Source
Project revenues / Rate
The main source of payment are the tolls collected by the concessionaire.

STATUS

Stage
  Execution
Substage
  Pre-Execution Activities
RELEVANT DATES
Request for proposals/Announcement August 09, 2022
Proposals Reception September 14, 2022
Ruling September 23, 2022
Contract Signing October 05, 2022
Term of the Contract October 07, 2075
Contractor
Controladora de Operaciones de Infraestructura, ICA Infraestructura  
Major Contractor’s Shareholders
Empresas Ingenieros Civiles Asociados

GEOLOCATION

State(s)
State of Mexico   

SPONSOR

Responsive image
Entity
State Government
Department
Secretaría de Movilidad
Sistema de Autopistas, Aeropuertos, Servicios Conexos y Auxiliares del Estado de México.
Contact
Jorge Iván Morales Pérez
E-mail
dirproy.saascaem@edomex.gob.mx

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The project aims to construct, operate, conserve, maintain and exploit the 82.80 kilometers Atlacomulco-Polotitlán highway, interconnecting municipalities in the northern zone of the State of Mexico in order to improve the quality of life of its inhabitants and as an alternative connection with neighboring states.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
State Government
ID
SMEM-CCA-01-2022
Announcement Bidding Website

REMARKS

The project originates from the presentation of the Unsolicited Proposal promoted by "Controladora de Operaciones de Infraestructura, S.A. de C.V." by means of a letter dated December 20, 2021 received on the aforementioned date.

Follow the Project

Leave your e-mail to receive updates on this Project.

 I have read and I accept the Privacy Notice