Project

CONSTRUCTION, OPERATION, EXPLOITATION, CONSERVATION AND MAINTENANCE OF THE ROAD DENOMINATED CUAPIAXTLA - CUACNOPALAN, BEGINNING AT THE JUNCTION OF CUAPIAXTLA II, IN THE STATE OF PUEBLA.

Sector: Transport


Last Revision

June 03, 2024
Short Name of the Project:
0909 Cuapiaxtla-Cuacnopalan Highway
Type of Investment:
Greenfield
Subsector:
Highways / bridges
Asset (s):
 Highway 63.66 KM-A2 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

2,500,000,000

Estimated Investment USD:

146,198,830

Banobras, Fonadin involvement Banobras/Fonadin involvement

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Design,  Construction,  Operation,  Maintenance,  Conservation,  Exploitation

DESCRIPTION

Build, operate, exploit, conserve and maintain the type A2 highway with high state jurisdiction specifications, denominated Cuapiaxtla - Cuacnopalan, approximately 63.66 km long, with its origin at the Cuapiaxtla II junction, located at km. 39,340 of the Amozoc - Perote Toll Highway and ending at km 203,500 of the Puebla - Orizaba Highway, in the states of Puebla and Tlaxcala, for a term of 30 years, according to the original concession title dated 12/23/ 2011.

Restatement of the title (01/22/2014). The title is restated in order to update terms.

Update of deadlines. Operate, conserve and maintain Section I of the A2 Cuapiaxtla Highway - State Limit, of 3,498 km; operate, conserve, exploit and maintain Section II of the A2 State Limit Highway - El Seco Junction, 22,701 km long; build, operate, conserve, exploit and maintain Section III of the A2 El Seco Junction - Cuacnopalan Highway, 37,461 km, in accordance with the first modification of the concession title dated 09/18/2018.

Second modification (09/10/2020). The financial model is updated.

i) Rehabilitation of the Cuapiaxtla-Entronque Audi-El Seco section, 26.16 km long.

ii) Construction of the 37.5 km "El Seco-Cuacnopalan" section.

(*) Project with Banobras and/or National Infrastructure Fund (Fonadin) involvement or support.
Included in a listed vehicle

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  State Concession
Term
30 years
Financing Sources
Private
100 %
MXN
2,500,000,000
USD
146,198,830
Payment Source
Rate
Payment fees charged by the concessionaire.

STATUS

Stage
  Execution
RELEVANT DATES
Contract Signing September 10, 2020
Execution/Construction Starting Date September 01, 2021
Term of the Contract September 01, 2051
Contractor
Concesionaria CUA  

GEOLOCATION

State(s)
Puebla, Tlaxcala   

SPONSOR

Responsive image
Entity
State Government
Department
Carreteras de Cuota Puebla
Contact
Emilia Velázquez Galindo
E-mail
evelazquez@ccp.gob.mx

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The purpose of the project is to improve the conditions of the road in the region to boost economic activity in Puebla and Tlaxcala, as well as the traffic and communication conditions in the surrounding municipalities.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
Secretaría de Medio Ambiente y Recursos Naturales
Description
Federal government entity and sectorial authority responsible for establishing the necessary criteria and instruments to guarantee the protection, preservation, and use of natural resources, by developing an environmental policy that ensures sustainable growth.
ID
21PU2011V0016
Permits

Follow the Project