Project
EXECUTION OF WORKS 274: ELECTRICAL SUBSTATIONS 1620 (2nd PHASE), IN THE STATE OF HIDALGO AND MEXICO CITY.
Sector: Electricity
Last Revision
October 25, 2024
Short Name of the Project:
0864 CFE: SE 1620 Valle de Mexico Distribution (Phase 2)
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
Power Station /Electrical Substation 9, Electric Power Transmission Line 2
Contract Currency:
US DollarsEstimated Investment MXN:
803,685,166
Estimated Investment USD:
46,999,132
Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
Design, Construction, Equipment, Installation