Project

CONSTRUCTION, MAINTENANCE AND EXPLOITATION OF RHE SIERVO DE LA NACION URBAN HIGHWAY (FELIPE ÁNGELES INTERNATIONAL AIRPORT CONNECTION) IN THE STATE OF MEXICO.

Sector: Transport


Last Revision

June 03, 2024
Short Name of the Project:
0816 Siervo de la Nacion Urban Highway
Type of Investment:
Brownfield
Subsector:
Highways / bridges
Asset (s):
 Highway 18.50 KM-A2 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

12,212,000,000

Estimated Investment USD:

714,152,046

Banobras, Fonadin involvement Banobras/Fonadin involvement

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Construction,  Maintenance,  Exploitation

DESCRIPTION

The project consists of the construction, maintenance and exploitation of the Río de los Remedios - Venta de Carpio - Gran Canal "Siervo de la Nación" Urban Highway, a 14 km eleveted viaduct of that connects in Ecatepec the Naucalpan-Ecatepec highway, the “Circuito Exterior Mexiquense” and the Mexico Tepexpan highway.
It includes five junctions: Rio de los Remedios, Alfredo del Mazo, Circunvalación Sur, Circuito Exterior Mexiquense and Jardines de Morelos.
FIRST AMENDING AGREEMENT (Dec. 15, 2014). The term of the contract is extended to 46 years from the day the concession title is signed.
THIRD AMENDMENT AGREEMENT (Sep. 15, 2021). Extension of the road to the Mexico - Pachuca Highway. Section II: Subsection from the Venta del Carpio Junction to the Mexico - Pachuca Toll Highway Junction, covering from km 13+772 to km 18+272 (4.5 km), and the contract term is extended to 60 years from the date of signing.

(*) Project with Banobras and/or National Infrastructure Fund (Fonadin) involvement or support.
Included in a listed vehicle

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  State Concession
Term
60 years
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
12,212,000,000
USD
714,152,046
Payment Source
Project revenues / Rate
The main source of payment are the tolls collected by the concessionaire.

STATUS

Stage
  Operation
Substage
  < 5 years of operation
RELEVANT DATES
Request for proposals/Announcement May 20, 2013
Ruling August 27, 2013
Contract Signing September 27, 2013
Execution/Construction Starting Date February 01, 2016
Operation Starting Date October 06, 2021
Contractor
Autopista Urbana Siervo de la Nación  
Major Contractor’s Shareholders
Mota Engil, Geoclasa, Marktorne

GEOLOCATION

State(s)
State of Mexico   

SPONSOR

Responsive image
Entity
State Government
Department
Sistema de Autopistas, Aeropuertos, Servicios Conexos y Auxiliares del Estado de México

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The project aims the expansion of the urban conectivity, the population mobility and the moving of products in the central region of the country.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
State Government
Responsive image
Source
Secretaría de Medio Ambiente y Recursos Naturales
Description
Federal government entity and sectorial authority responsible for establishing the necessary criteria and instruments to guarantee the protection, preservation, and use of natural resources, by developing an environmental policy that ensures sustainable growth.
ID
15EM2014V0025
Permits
Responsive image
Source
Fonadin
Description
National Infrastructure Fund that supports the development of communications, transport, water, environmental and tourism sectors by providing grants, venture capital, subordinated debt, credit and guarantees for the design and execution of high impact infrastructure projects.

REMARKS

The commencement of works for the 4.5 km expansion was on Sep. 06, 2022, and the right-of-way clearance is ongoing.